Next steps and expected dates (timelines are approx and may change)
- [x] Poron in house testing (Feb 2023)
- [x] Gasket material calculated and ordered (Feb 2023)
- [x] Gasket Material production of parts complete (March 2023)
- [x] PCB’s ordered, lead time 4-6 weeks (Feb 2023)
- [x] PCB’s shipped to PT (April 2023)
- [x] Packing materials ordered, lead time 1 week (March 2023)
- [x] Production complete (expected February 2023) - Delayed - awaiting update
- [x] Manufacturer final QC and packing (April 2023)
- [x] Shipping to PT in china, lead time 1 week (Late April 2023)
- [x] Shipping to PTHQ in UK, approx 4-6 weeks transit time (TBC 2023)
- [x] Expected to arrive at port 9th June, PTHQ 14 days later
- [x] QC Start (26th June 2023) - Started early, 22nd June
- [x] QC Finish (est 9th July 2023)
- [x] Replacement JST connectors arrive (estimated 10th July)
- [x] Replacement Silicone sheets arrive (estimated 21st July)
- [x] All boards ship to customers (Late July 2023)
- [x] Emailed customers completed (Late July/Early August)